199 Street—23 Ave To 35 Ave Project

Project Description:

Earthworks and underground utility installation to upgrade a rural collector road to an urban arterial c/w Sanitary, Storm, Water Transmission Main and Creek Crossing. Existing roadway where traffic had to be maintained.

Installation of 1600 lm of 600 mm water transmission main both open cut and cased c/w valves, hydrants, fittings, etc. Installation of 65 lm of 600 mm insulated, stainless steel waterman for a creek crossing c/w heat tracing. Construction of 800 square meter bridge c/w retaining walls.

Project Statistics:

Z

Location :

Edmonton, AB
Z

Duration :

September 2016 – October 2017
Z

Owner :

Qualico

Our Services:

  • ZEarthworks
  • ZUnderground Utilities

Scope of Work

  • Z1,600 lm - Water Pipe (600mm Transmission Open Cut & Case Bore)
  • Z1,600 lm - Water Pipe (600mm Transmission Open Cut & Case Bore)
  • Z1,540 lm - Sewer Pipe (200mm - 750mm)
  • Z300,000 m3 - Grading
  • Z800 m2 - Bridge w/ Retaining Wall
  • Z120 lm - 3000m Culvert