Aster Stage 2/1/4

Project Description:

The project involved 130,000m3 of topsoil and marginal stripping to stockpile, 170,000m3 of common ex from SWMF, 185,000 m3 of engineered fill and over 20,000m2 of subgrade completed. Over 4 km of pipe installed with 35 manholes, 1800mm dia. concrete pipe, large diameter storm and sanitary trunks, deep 525mm sanitary tie-in next to existing 450mm water valve required 8m deep slide rail trench box install, crossed shallow utilities with 1800mm storm, installed 450mm watermain.

Overall a very challenging project with bad ground conditions and 40+ rain days, project was completed on schedule.

Project Statistics:

Z

Location :

Edmonton, AB
Z

Duration :

Sept 2019 – Nov 2020
Z

Owner :

Qualico

Our Services:

  • ZEarthworks
  • ZUnderground Utilities

Scope of Work

  • Z134,000 m3 – Topsoil Stripping and Marginal Stripping
  • Z85,000 m3 – Common Ex from SWMF
  • Z80,000 m3 – Common Ex onsite
  • Z20,000 m2 – Subgrade Prep
  • Z185,000 m3 – Engineered Fill
  • Z4,000+ lm – Sanitary, Water, Storm Pipe
  • Z35 manholes, 1800mm concrete pipe and box manhole