Project Description:
The project involved 44,000m3 of organic stripping, 17,000m3 of onsite common ex and 34,000m3 of common import. Over 1000 lm of sanitary, storm and water main installed including 70lm of case bore under Hwy 39/50Ave and 9m deep manhole tie-in on Hawthorne way.
Finishing the project with over 3,400m3 of sub-grade, base and paving, over 50,000m3 of landscape work and traffic signal modification and installation, and 50 Ave and 69 St lane painting and traffic signs installation.
Project Statistics:
Location :
Leduc, AB
Duration :
Aug 2020 – Nov 2020
Owner :
City of Leduc
Our Services:
- ZEarthworks
- ZUnderground Utilities
Scope of Work
- Z44,000 m3 – Topsoil and marginal stripping
- Z51,000 m3 – Common earthworks
- Z1050 lm – Sanitary, Storm and Water mains
- Z3,400 m2 – Subgrade, Base and Paving
- Z70 lm – 1200mm Case Bore
- Z52,000 m2 – Topsoil Placement and Seed Application
- Z3 EA – Traffic Signal Modifications and Installations