Ekota Dry Pond and Menisa Storm Relief

Project Description:

Earthworks and underground utility installation to meet 1:100 year storm requirements. Work area included: residential areas, existing roadways, adjacent to a school, through natural park areas.

Public consultation and notifications. Existing water & sewer remained live during new line installation. Successfully met tight timelines to complete project before school resumed. Temp Servicing for Residential Area.

Project Statistics:

Z

Location :

Edmonton, AB
Z

Duration :

May 2018 – October 2017
Z

Owner :

EPCOR

Our Services:

  • ZEarthworks
  • ZUnderground Utilities

Scope of Work

  • Z95,000 m3 - Common Excavated Earthworks For Pond
  • Z95,000 m3 - Common Excavated Earthworks For Pond
  • Z600 lm - Storm Pipe Through Existing Roadway
  • Z75% - Excavation Trenching Required Shoring
  • Z1 ls - Site Rehabilitation, Traffic Management And Landscaping
  • Z1 ls - Removal And Installation Of Electrical Services & Lighting