Project Description:
Sureway was contracted by Enbridge for tank lot construction, including all mechanical, electrical and civil construction to the containment limits.
Project Statistics:
Location :
Hardisty, AB
Duration :
August 2017 – May 2018
Owner :
Enbridge
Our Services:
- ZMechanical
- ZUnderground Utilities
- ZMechanical
Scope of Work
- Z1,000 m3 - HDPE firewater installation
- Z14 Ha - Clearing, stripping and grading
- Z3.7 Ha - Lining containment
- ZBuilding demolition, building grading, structural fabrication for tank lot access
- ZConstruction of 3 tank foundations
- ZFinal grading and gravel for tank lot, laydown and access roads
- ZInstallation and coating for tank piping including riser fabrication for 3 tanks
- ZTank lot electrical installation
- ZTank lot piling