Project Description:
Earthworks and underground utility installation of an Industrial Subdivision. Stripped 170,000m3 of topsoil (Offsite haul of 150,000m3 of topsoil). Excavated 530,000m3 of material to grade industrial lots, roads and two storm ponds.
Installation of storm main, sanitary main, water main, services, Oil & Grit Separator, Control Manhole and a Valve Chamber. Scope required Atco Gas, Alta Link, CN work agreements, On-Street Construction Permit and Erosion Sediment Control Maintenance.
Project Statistics:
Location :
St. Albert, AB
Duration :
April – September 2015
Owner :
QuadReal Property Group
Our Services:
- ZEarthworks
- ZUnderground Utilities
Scope of Work
- Z400,000 m3 - Topsoil stripping(Offsite Haul 150,000m3)
- Z400,000 m3 - Topsoil stripping(Offsite Haul 150,000m3)
- Z1,700 lm - Storm Pipe (300mm - 1950mm)
- Z1,400 lm - Sanitary Pipe (200mm - 3750mm)
- Z1,900 lm - Water Pipe (200mm - 450mm) (700mm - 450mm)
- Z1 ls - Control Structure, Valve Chamber, Oil & Grit Separator