Project Description:
As the Prime Contractor, Sureway Industrial Services Ltd. was contracted by Trans Canada for the Greenfield installation of a 15 megawatt natural gas compressor station, from piling stage through to commissioning and final grading/fencing.
Project Statistics:
Location :
180Km NW of Manning, AB
Duration :
2014-2015
Owner :
TC Energy
Our Services:
- ZMechanical
Scope of Work
- ZNPS 2 – NPS 42 Yard and facility piping
- Z700 rig mats utilized full-time during construction
- Z61,000 m3 of fill added to allow site water control system functionality
- ZFull ASME Quality Audit performed onsite – received highest mark given on 200,000 sites by USA Audit Team
- ZFull NEB Audit performed during shop fabrication – received full pass by Government Audit Team.
- ZPeak manpower of approximately 200 personnel