by Kacper Sikora | Dec 10, 2021
Project Description: This project was part of the Regional Municipality of Wood Buffalo’s latest Master Water and Master Wastewater plans to update Fort McMurray’s aging infrastructure. In 2015, Sureway was retained by the RMWB with Urban Systems as the municipality’s...
by Kacper Sikora | Dec 10, 2021
Project Description: Earthworks and underground utility installation of an Industrial Subdivision. Stripped 170,000m3 of topsoil (Offsite haul of 150,000m3 of topsoil). Excavated 530,000m3 of material to grade industrial lots, roads and two storm ponds. Installation...
by Stephen Mccue | Sep 23, 2020
Sureway’s Role: In 2018 Sureway was awarded the contract for the development of a new mine expansion area, Pit 09. Sureway completed the tree clearing for this expansion in 2017. Work scope included reclamation salvage of topsoil and peat, drainage establishment...
by Stephen Mccue | Nov 9, 2017
Specifications : This was a complete installation of a Solar Titan Turbine Compressor Station from the ground up. A project of this magnitude was a large undertaking but with the right team members and office support, we were able to overcome any obstacle. Being a...
by Stephen Mccue | Nov 9, 2017
Project Information : Z Project Class : Industrial Z Client : Paramount Resources Ltd. Z Municipality : Northern Z Province : AB Z Address : Remote Specifications: This project is a mid-winter planned one-week Gas Plant Shutdown and Maintenance Turnaround near the NWT...